Plan engineering activities in the Tram and Tramway environment
Overview
This standard is about planning engineering activities in the Tram and Tramway environment. It is about being able to access the relevant information regarding the activities to be undertaken and determine the resources required. You will know the type and range of plans to be produced and will ensure that the information gathered is relevant to the work to be carried out. You will be able to take into account the activities to be undertaken and the limitations of the work environment. The complexity of the plan will depend on the nature or size of the activity to be undertaken. You will know and understand how to prioritise activities and how to adapt and change plans when objectives cannot be achieved.
This standard is for those who work as a technician or supervisor in the engineering or construction Tram and Tramway environment.
Performance criteria
You must be able to:
P1 identify and analyse the relevant information required for the engineering activity
P2 identify the relevant health and safety procedures that must be followed
P3 confirm the engineering activities to be carried out and determine their sequence
P4 establish the methods and techniques required to complete the engineering activities
P5 identify and confirm the resources required
P6 identify when resources are not available and deal with the deficiency in line with organisational procedures
P7 confirm the timescales required for the engineering activity
P8 prepare a work plan that meets organisational requirements and procedures
P9 confirm alternative solutions where planned engineering activities cannot be achieved in line with organisational procedures
Knowledge and Understanding
You need to know and understand:
K1 the importance of planning engineering activities that follow the relevant Health and safety procedures approved by your organisation K2 the types of resources that can be used during engineering activates in the Tram and Tramway environment K3 how to allocate and confirm resources within your own area of responsibility K4 the different **types of engineering plans** required for engineering activities in the Tram and Tramway environment K5 the relevant **methods and techniques** that can be used when planning engineering activities in the Tram and Tramway environment K6 how to **prepare** a plan that meets organisational procedures K7 how to prioritise engineering activities to achieve the **objectives** of the engineering plan K8 the circumstances when planned engineering activities cannot be achieved K9 how to adapt and change plans when engineering activities cannot be achieved in line with organisational procedures |
Scope/range
Scope Performance
P1 **Information** may include; financial information, methods statements, specifications, risk assessments, instructions, asset management system. P2** ** **H****ealth and safety procedures** may include; local safety certificates, safe systems of work, personal protective equipment, risk assessments, environmental conditions, hazards, working time and breaks, moving and manual handling, personal track safety, competency requirements. P5 **Resources** may include; documentation, tools, plant, equipment (calibrated and serviceable), replacement components, materials, consumables, communications equipment, safe systems of work equipment, personnel, workspace/area, support from other departments/teams/outside stakeholders. |
Scope Knowledge
K4 Types of engineering plans may include; lifting plans, maintenance activities, testing and trialling, research and development, new product/component introduction, logistical operations, site facilities and access, modification and repair activities, assemble activities, installation activities, diagnostic activities, finishing activities, cleaning activities.
K5 M*ethods and techniques* may include; activity planning (charts, check lists, logs), project start and delivery time/milestones, key performance indicators, budgeting, quality measuring and control, resource allocation, communication strategies, risk management, identification of roles and responsibilities, contingency planning.
K6 Prepare may include; presentation, structure, style, clarity.
K7 Objectives may include; cost, efficiency, quality, timescales.
Values
Behaviours
Skills
Glossary
Tram
Tramcars, tram vehicle, and any other rail vehicles that operate on tramways. It includes one or more trams coupled together and includes non-passenger-carrying vehicles.
* *
Tramway environment
Includes the tramway (a set of rails, switches and crossings which form the route of a Tram) , infrastructure (fixed assets used for the running of the Tram transport system, including, the tramway, bridges, tunnels, stops, stations and fixed equipment for signalling, communications and electrification), depots, stabling yards.