Overhauling marine ancillary plant and equipment

URN: SEMME3127
Business Sectors (Suites): Marine Engineering Suite 3
Developed by: Enginuity
Approved on: 31 Mar 2019

Overview

This standard identifies the competences you need to carry out a complete overhaul of marine ancillary plant and equipment, in accordance with approved procedures. The equipment to be overhauled will have been removed from the vessel or craft and the overhauling activities may take place in a shipyard or manufacturer's workshops. The marine ancillary plant and equipment covered by this standard includes items such as garbage disposal compactors, sewage treatment plants, reverse osmosis plant, incinerators, laundry and medical equipment and evaporators. The overhauling activities will involve stripping the equipment down to component level, cleaning and inspecting the components for wear, replacing all defective and `lifed' components and rebuilding the equipment in line with the overhauling specification.

The marine ancillary plant and equipment to be overhauled could include pipework, pre-heaters, drain coolers, control valves, pumps, seals, instrumentation, stops, filters, strainers, macerators, tanks, emergency stops, mechanical and electrical controls, safety devices and other associated mechanical items. The overhauling activities will include making all necessary checks and adjustments to ensure that components are correctly replaced, positioned, aligned, adjusted, torque loaded, locked and fastened and that the correct sealants are used.

Your responsibilities will require you to comply with organisational policy and procedures for the overhauling activities undertaken and to report any problems with these activities or with the tools and equipment used that you cannot personally resolve, or are outside your permitted authority, to the relevant people. You must ensure that all tools, equipment and materials used in the overhauling activities are removed from the work area on completion of the activities and that all necessary job/task documentation is completed accurately and legibly. You will be expected to work with a minimum of supervision, taking personal responsibility for your own actions and for the quality and accuracy of the work that you carry out.

Your underpinning knowledge will provide a good understanding of your work and will provide an informed approach to applying overhauling procedures to marine ancillary plant and equipment. You will understand the dismantling/reassembly methods and procedures used and their application. You will know how the equipment functions, the purpose of the individual components and associated defects, in adequate depth to provide a sound basis for carrying out the overhauling activities, correcting faults and ensuring that the repaired equipment functions to the required specification. In addition, you will have sufficient in-depth knowledge of these components to ensure that they are fit for purpose and meet the specifications, thus providing a sound basis for carrying out reassembly.

You will understand the safety precautions required when carrying out the maintenance activities associated with marine ancillary plant and equipment, especially those for lifting and handling the equipment. You will be required to demonstrate safe working practices throughout and will understand your responsibility for taking the necessary safeguards to protect yourself and others in the workplace, both ashore and afloat.


Performance criteria

You must be able to:

  1. work safely at all times, complying with health and safety and other relevant regulations, directives and guidelines

  2. follow the relevant maintenance schedules to carry out the required work

  3. carry out the maintenance activities within the limits of your personal authority
  4. carry out the maintenance activities in the specified sequence and in an agreed time scale

  5. report any instances where the maintenance activities cannot be fully met or where there are identified defects outside the planned schedule

  6. complete relevant documentation in line
    with organisational procedures, 
    and pass them on to the appropriate person
  7. dispose of waste materials in accordance with safe working practices and approved procedures

Knowledge and Understanding

You need to know and understand:

  1. the health and safety requirements of the area in which the overhauling activity is to take place and the responsibility they place on you
  2. the specific health and safety precautions to be applied during the overhauling procedure and their effects on others
  3. hazards associated with carrying out overhauling activities on marine ancillary plant and equipment (such as using lifting and handling equipment, handling oils and greases, release of stored pressure/force, misuse of tools, using damaged or badly maintained tools and equipment, not following laid-down overhauling procedures)
  4. the importance of wearing protective clothing and other appropriate safety equipment (PPE) during the overhaul

  5. how to obtain and interpret drawings, specifications, manufacturers' manuals and other documents needed in the overhauling process

  6. how to carry out currency/issue checks of the specifications you are working with
  7. the procedure for obtaining replacement parts, materials and other consumables necessary for the overhaul
  8. company policy on the repair/replacement of components during the overhauling process
  9. the sequence to be adopted for the dismantling/reassembling of various types of assemblies
  10. the methods and techniques used to dismantle/reassemble marine ancillary plant and equipment (such as release of pressures/force, proof-marking, extraction, pressing, alignment)
  11. methods of checking that components are fit for purpose, how to identify defects and wear characteristics and the need to replace `lifed' items (such as seals, filters and gaskets)
  12. how to make adjustments to components/assemblies to ensure that they function correctly (such as setting working clearance, setting travel, setting backlash in gears, pre-loading bearings)
  13. the basic principles of how the equipment functions, its operating sequence, the working purpose of individual units/components and how they interact
  14. the identification, application, fitting and removal of different types of bearings (such as roller, ball, thrust, shell)
  15. methods and techniques of fitting keys and splines
  16. the identification, application, fitting and removal of different types of gears
  17. how to set up timing marks and position and set the tension of belts and chains, correctly
  18. the identification and application of different types of locking devices
  19. the uses of measuring equipment (such as micrometers, verniers, expansion indicators and other measuring devices) 
  20. how to check that tools and equipment are free from damage or defect, are in a safe and usable condition and are configured correctly for the intended purpose
  21. the generation of technical documentation and/or reports following completion of the overhauling activity
  22. the equipment operating and control procedures to be applied during the overhauling activity
  23. how to use lifting and handling equipment in the overhauling activity
  24. the problems associated with the overhauling of marine ancillary plant and equipment and how they can be overcome
  25. the organisational procedure to be adopted for the safe disposal of waste of all types of materials
  26. the extent of your own authority and to whom you should report if you have a problem that you cannot resolve

Scope/range


Scope Performance

  1. Carry out all of the following during the overhaul of the marine ancillary plant and equipment:

    1. use the correct issue of company and/or manufacturers' drawings and overhauling documentation
    2. adhere to risk assessment, COSHH and other relevant safety standards
    3. ensure the safe isolation of equipment (such as mechanical, electricity, gas, air or fluids, steam)
    4. provide safe access and working arrangements for the overhauling area
    5. use lifting and handling equipment, in accordance with health and safety guidelines and procedures
    6. carry out the overhauling activities using appropriate techniques and procedures
    7. comply with organisational requirements with regard to renewal or replacement of existing components
    8. ensure that the overhauled components meet the required specification
    9. ensure that there are no foreign objects left in the completed equipment
  2. Carry out overhauling activities on all the machinery within one of the following sets of marine ancillary plant and equipment:

    1. garbage compactor, garbage disposal unit and incinerator   
    2. reverse osmosis plant
    3. hospital or sickbay and dental                                            
    4. evaporators
    5. sewage treatment plant                                                     
    6. laundry
  3. Carry out overhauling activities on four of the following marine ancillary plant and equipment components:

    1. pre-heater              
    2. instrumentation   
    3. macerator                  
    4. washing machine
    5. drain cooler                 
    6. pipe-work                 
    7. tank                           
    8. tumble drier
    9. fresh water pump     
    10. mechanical stops   
    11. compactor mechanism   
    12. sink/sluice
    13. sea water pump          
    14. air ejector               
    15. press                      
    16. isolating valve
    17. mechanical controls    
    18. exhaust                     
    19. furnace                      
    20. damper
    21. compressor               
    22. safety trips         
    23. electro-mechanical trips     
    24. x-ray machine
  4. Carry out eighteen of the following activities on the equipment being overhauled:

    1. dismantling equipment to unit/sub-assembly level    
    2. tightening fastenings to the required torque
    3. dismantling units to component level                        
    4. applying gaskets and sealant/adhesives
    5. proof-marking/labelling of components                    
    6. bedding in of white metal bearings
    7. checking components for serviceability                    
    8. lapping in valves
    9. replacing all `lifed' items (such as seals, bearings, gaskets)  
    10. setting working clearance
    11. replacing all damaged or defective components            
    12. electrical bonding of components
    13. setting timings and adjusting replaced components      
    14. making `off-load' checks before starting up
    15. re-assembling components to sub-assembly level        
    16. replenishing oils and greases
    17. re-assembling sub-assemblies to unit level                    
    18. securing components using mechanical fasteners and threaded devices
    19. applying bolt locking methods (such as split pins, wire locking, lock nuts, stiff nuts, swage nuts)
    20. functionally testing the completed system
  5. Replace a range of marine ancillary plant and equipment components, to include sixteen of the following:

    1. shafts                                  
    2. shell bearings               
    3. slides
    4. couplings                             
    5. bearing housings          
    6. rollers
    7. gears                                 
    8. keys                        
    9. safety trips
    10. brakes                        
    11. springs          
    12. static and dynamic seals
    13. valves and seats              
    14. diaphragms               
    15. housings
    16. splines                               
    17. cams and followers    
    18. actuating mechanisms
    19. roller or ball bearings         
    20. chains and sprockets        
    21. structural components
    22. pipes and unions                
    23. pulleys and belts           
    24. wire thread inserts
    25. strainers and filters             
    26. levers and linkages    
    27. door seals
    28. hoses                             
    29. shims and packing        
    30. float mechanisms
    31. locking and retaining devices (such as circlips, pins)         
    32. other specific components
  6. Overhaul marine ancillary plant and equipment, in compliance with one of the following standards:

    1. BS or ISO standards and procedures
    2. customer (contractual) standards and requirements
    3. company standards and procedures
    4. specific system requirements
    5. recognised compliance agency/body's standards
    6. other accepted international standards
  7. Complete the relevant documentation in line
    with organisational procedures, 
    to include one from the following and pass it to the appropriate people:

    1. job cards
    2. permit to work/formal risk assessment
    3. maintenance log or report
    4. chart of dimensional inspection
    5. other specific reporting method

Scope Knowledge


Values


Behaviours

Behaviours:

You will be able to apply the appropriate behaviours required in the workplace to meet the job profile and overall company objectives, such as:

  • strong work ethic
  • positive attitude
  • team player
  • dependability
  • responsibility
  • honesty
  • integrity
  • motivation
  • commitment

Skills


Glossary


Links To Other NOS


External Links


Version Number

3

Indicative Review Date

29 Apr 2021

Validity

Current

Status

Original

Originating Organisation

Semta

Original URN

SEMME3127

Relevant Occupations

Marine Engineering Trades

SOC Code

5235

Keywords

engineering; marine; overhaul; ancillary plant; equipment; garbage disposal; sewage treatment; reverse osmosis; incinerators; laundry; medical equipment