Overview

This standard covers the competences required to lead total productive maintenance (TPM) activities on equipment and processes, and aims to prevent equipment problems by identifying potential causes rather than waiting for a problem to occur. It involves the measurement of the six classic hidden losses, assessment of potential and priorities for loss reduction. It covers the application of the TPM principles and processes to resources, such as plant and equipment, machines, office equipment, service equipment and utilities. It also concerns assessment of the equipment/process condition, the steps required to restore the equipment/process to good working order, and then to set a robust asset care regime to maintain this condition.

You will be required to lead the application of the appropriate TPM techniques, and to use the data gathered on the resource to refine the working practices through the application of autonomous, condition based and planned maintenance. Working practice improvement will include cleaning and checking, early problem detection and process monitoring, and routine servicing. This will involve close working with both production and maintenance staff, and will include cross-shift implementation (if applicable to your organisation).

Your responsibilities will require you to comply with organisational policy and procedures for the activities undertaken, and to report any problems that you cannot solve, or that are outside your responsibility, to the relevant authority.  You will also be responsible for ensuring that all tools and equipment used during the maintenance activities are correctly accounted for, and that all necessary job/task documentation is completed accurately and legibly. You will be expected to take full responsibility for your own actions within the activity, and for the quality and accuracy of the work that you carry out.

Your underpinning knowledge will provide a good understanding of your work, and will provide an informed approach to the TPM techniques and procedures used. You will need to understand the principles and procedures of TPM, and its application, in adequate depth to provide a sound basis for carrying out the activities to the required criteria.

Applying and advising on safe working practices will be a key issue throughout.


Performance criteria

You must be able to:

  1. work safely at all times, complying with health and safety and other relevant regulations, directives and guidelines
  2. approve the selection of the appropriate asset on which to carry out the total productive maintenance activity
  3. obtain and approve the necessary information to carry out the activity
  4. lead the total productive maintenance activity using the appropriate techniques
  5. use the overall equipment effectiveness (OEE) measure and information to confirm which elements of the OEE and their associated losses need improvement
  6. approve and use an action plan which will reduce/eliminate the losses, and hence improve the overall equipment effectiveness
  7. lead the implementation and monitoring of improvements to working practices through the total productive maintenance activities

Knowledge and Understanding

You need to know and understand:

  1. how to work safely at all times, complying with health and safety and other relevant regulations, directives and guidelines
  2. how to plan the resources and time needed to carry out the agreed activity
  3. the principles of TPM, and how they can be applied in administration procedures, safety improvement and quality maintenance
  4. how to select an asset on which to carry out the TPM activity
  5. how to implement a systematic and structured approach to carrying out autonomous, condition based and planned maintenance
  6. the difference between a chronic and sporadic loss, and the countermeasures to both
  7. how to calculate overall equipment effectiveness (OEE)
  8. where to find the information required to calculate the OEE for the chosen asset
  9. the benefits of having a TPM system
  10. the importance of taking ownership of the TPM system, and the issues that can be expected to be resolved
  11. the six major losses and how loss-reduction actions need to be prioritised
  12. the use of standard operating procedures, single point lessons and machine/process start-up and shutdown procedures
  13. an awareness of the improvement activities that will drive the implementation of the TPM activities (Kaizen, team working)
  14. critical processes and early problem detection steps
  15. loss areas and opportunities for improvement
  16. standards of wear, and the ability to stabilise the component life
  17. the techniques of visual management used to communicate the information and results obtained by this process (including TPM activity boards and checklists)
  18. the integration with workplace organisation and improving OEE
  19. contaminants and sources of contaminants
  20. the extent of your own authority, and to whom you should report in the event of problems that you cannot resolve

Scope/range


Scope Performance

1.    Lead the activities within your area of responsibility to include all of the following:

    1. set out and communicate the purpose of the improvement activities
    2. involve the team in planning how the improvement activity will be achieved
    3. ensure each team member has individual objectives and understands how these objectives contribute to the overall improvement objective
    4. provide advice and support the team to achieve both team and individual improvement objectives
    5. motivate the team to present their own improvement ideas
    6. encourage the team and/or individuals to take the lead where appropriate
    7. agree the implementation of the improvement ideas
    8. negotiate any physical and/or financial resources required to implement the improvement activity (where appropriate)
    9. monitor the progress of improvement activities
    10. deal with any organisational problems identified during the improvement activity

 

2.    Lead the total productive maintenance process on two assets from the following:

    1. plant and equipment
    2. machines
    3. office equipment
    4. service equipment
    5. utilities

       

3.    Lead the total productive maintenance process, and show how one of the following is undertaken:

    1. assess criticality of equipment/process condition and identify refurbishment needs
    2. identify an integrated asset care plan for both operator and maintenance staff

       

       

4.    Lead the collection of information relating to all of the following:

    1. load or demand
    2. capacity
    3. Takt time or bottleneck analysis

       

5.    Lead all of the following total productive maintenance activities:

    1. autonomous maintenance (front line asset care)
    2. condition based maintenance (predictive)
    3. planned maintenance steps (fixed interval)

       

6.    Confirm improvements to working practices through three of the following:

    1. initial cleaning
    2. countermeasures for cause and effect of dust and dirt
    3. cleaning and lubrication standards
    4. general inspection
    5. autonomous inspection
    6. workplace organisation
    7. full circle implementation of autonomous maintenance



Scope Knowledge


Values


Behaviours


Skills


Glossary


Links To Other NOS


External Links


Version Number

3

Indicative Review Date

2028

Validity

Current

Status

Original

Originating Organisation

Enginuity

Original URN

SEMBIT413

Relevant Occupations

Associate Professionals and Technical Occupations, Business and Finance Associate Professionals, Business Management, Business, Administration and Law

SOC Code

2127

Keywords

engineering; business; improvement; techniques; total productive maintenance; TPM; production losses; equipment conditioning; care regime