Carrying out project management of aeronautical engineering activities

URN: SEMAE3196
Business Sectors (Suites): Aeronautical Engineering Suite 3
Developed by: Enginuity
Approved on: 2021

Overview

This standard identifies the competences you need to project manage aeronautical engineering activities, time and resources, in accordance with approved procedures. You will be required to ensure that the project management activities are capable of meeting the aeronautical engineering requirements, and that the plans effectively integrate with existing processes. The scope of the standard requires you to produce project plans for significant aeronautical engineering processes with complex requirements having multiple operations and resources, and will cover such items as component/product manufacturing, installation and commissioning, testing and trialling, planned maintenance, and plans for capability studies or equipment replacement programs.

Your responsibilities will require you to comply with organisational policy and procedures for project managing the engineering activities. You will report any problems with the activities that you cannot personally resolve, or that are outside your permitted authority, to the relevant people. You will be expected to work with a minimum of supervision, taking personal responsibility for your own actions and for the quality and accuracy of the work that you carry out.

Your underpinning knowledge will provide a good understanding of your work and will provide an informed approach to applying project planning procedures to aeronautical engineering activities. You will understand the project planning process and its application, and will know about the aeronautical engineering activities within your organisation, in adequate depth to provide a sound basis for carrying out the project planning activities to the required standard. You will understand your organisation's methods of operation in sufficient detail to enable you to make informed decisions.

You will be aware of any health, safety and environmental requirements applicable to the aeronautical engineering activities being project managed. You will be required to demonstrate safe working practices throughout, and will understand the responsibility you owe to yourself and others in the workplace.


Performance criteria

You must be able to:

  1. confirm the operational activities that are required to achieve the operational methods and procedures
  2. identify the most suitable sequence of operational activities
  3. schedule the time and resources available for undertaking the operational activities
  4. ensure that operational schedules are capable of meeting all relevant requirements
  5. incorporate new operational schedules into the operational process with minimum disruption
  6. produce project management plans
  7. identify potential difficulties and produce appropriate contingency plans
  8. ensure that operational plans comply with all relevant regulations and guidelines
  9. specify clearly the operational plans and record them in the appropriate information systems

Knowledge and Understanding

You need to know and understand:

  1. how to access information on health and safety regulations and guidelines relating to the engineering activities to be project managed
  2. the implications of not taking account of legislation, regulations, standards and guidelines when producing the project plans
  3. the requirements and importance of understanding and applying human factors as defined by the regulatory requirements and the potential impact if these are not adhered to
  4. how to obtain information on the activity to be planned and the type of information that is available (such as customer order requirements and instructions, quality control requirements, product specification, manufacturing methods)
  5. how to access and use the appropriate information and documentation systems
  6. how to interpret engineering schedules and the techniques used for project management and planning activities
  7. the types of data that should be included in the project plans (such as time scales, resource requirements, health and safety issues)
  8. the document formats, codes and conventions that are used in preparing the project management plans
  9. the factors to be taken into account when preparing the project management plans, especially those covering working conditions and safety
  10. how to assess resource requirements, and the main types of resources involved with different types of engineering activity and the typical timescales for providing them
  11. how to plan resources
  12. the obvious (and hidden) costs of resources/activities
  13. the normal timescales for carrying out specific engineering activities and how and why they vary
  14. the methods and techniques for capacity planning
  15. the products (or assets) involved in the activity being planned and their availability
  16. the development of the project management plans (to include both master documents and working instructions, along with their purpose, content and status)
  17. how to prepare the project management plans (to include the structure, style, clarity and compliance with relevant standards)
  18. the process used in the organisation to validate the project management plans produced
  19. the control procedure for ensuring that the project management plans are maintained up to date
  20. the procedures for changing the project management plans and why control procedures are used
  21. the importance of maintaining records, what needs to be recorded and where records are kept
  22. why contingency plans need to be drawn up and how to develop them
  23. whom to inform about the project management plans
  24. the different ways of presenting information to different people
  25. the importance of providing the right information at the right time
  26. the roles and responsibilities of key personnel in your organisation
  27. the problems that can occur during the implementation of the project management plans and how these problems can be rectified
  28. the sources of technical expertise if you have problems that you cannot resolve
  29. the organisational procedures for providing information to different people
  30. the extent of your own authority and to whom you should report in the event of problems that you cannot resolve

Scope/range


Scope Performance

  1. Carry out all of the following when producing the project management plans:

    1. use the correct issue of company information
    2. collect relevant information on the engineering requirements, operations, methods and resources
    3. determine the availability of resources required
    4. ensure that health and safety regulations and safe working practices are taken into account
    5. ensure that the influence of working conditions is recognised and included in the schedules
    6. present the engineering plans in the appropriate formats
  2. Produce project plans and carry out project management of two of the following:

    1. drawing/design activities (such as electronic components, printed circuit boards, thick, thin or flexible film circuits)
    2. manufacturing activities (such as machining, detail fitting, fabrication of components, moulding)
    3. mechanical assembly activities (such as mechanical, structural, fluid power)
    4. electrical/electronic assembly activities (such as avionic)
    5. installation activities (such as mechanical equipment installation, electrical/avionic installation)
    6. lifting and moving large components/assemblies (including transportation/delivery)
    7. finishing activities (such as stripping finishes, painting, plating, anodising)
    8. material processing activities (such as heat treatment, annealing)
    9. modifications and repair activities (such as airframe, systems, avionics)
    10. materials handling (such as movement of materials, materials storage, removal of waste)
    11. operational activities (such as quality systems and audit, scheduled safety audits and risk assessments)
    12. maintenance activities (such as planned preventive maintenance, part/sub assembly exchange, breakdown response, maintenance records systems, line setting)
    13. equipment capability/performance measurement
    14. plant and equipment (such as plant layout, equipment changeover, equipment replacement)
    15. testing and trialling
    16. commissioning/decommissioning
    17. research and development
  3. Obtain accurate details of activities and resources from two of the following people or departments:

    1. management/directors        
    2. design office      
    3. industrial engineering
    4. client/customer                 
    5. suppliers          
    6. process engineering
    7. quality engineering          
    8. plant engineering    
    9. purchasing
    10. sales                            
    11. production engineering      
    12. safety engineering
  4. Prepare and review plans of resources, to include five of the following:

    1. people with the necessary skills 
    2. facilities                                 
    3. financial
    4. materials                              
    5. space
    6. equipment                          
    7. support services
  5. Identify any difficulties and produce a contingency plan detailing one of the following actions, to ensure that the project plans meet requirements:

    1. agree revised requirements with management/client
    2. change timescales in agreement with management/clients
    3. reschedule
    4. obtain additional/alternative resources
    5. recommend a change to the process
    6. other specific actions
  6. Record and present the project plans to the appropriate people, by the following methods:

    1. verbally

Plus by one other method from the following:
2. written/typed report
3. specific company documentation
4. electronic mail
5. computer-based presentation 
6. other appropriate media


Scope Knowledge


Values


Behaviours

You will be able to apply the appropriate behaviours required in the workplace to meet the job profile and overall company objectives, such as:

  • strong work ethic
  • positive attitude
  • team player
  • dependability
  • responsibility
  • honesty
  • integrity
  • motivation
  • commitment

Skills


Glossary


Links To Other NOS


External Links


Version Number

3

Indicative Review Date

2024

Validity

Current

Status

Original

Originating Organisation

Enginuity

Original URN

SEMAE3196

Relevant Occupations

Engineer, Engineering, Engineering and Manufacturing Technologies, Engineering Technicians

SOC Code

5234

Keywords

project management; aeronautical; engineering activities; component or product manufacturing; installation and commissioning; testing and trialling; planned maintenance