Overview
This Standard is about commissioning networks in the water industry. It includes obtaining necessary resources, ensuring conditions are suitable, following commissioning procedures, resolving problems, making sure networks comply with relevant specifications, regulations and guidelines and recording results.
This Standard will apply to water network construction operations and is intended for construction supervisors.
Performance criteria
You must be able to:
- specify the approved procedures and practices for commissioning networks
- identify commissioning methods that are suitable to the network
- confirm that environment is suitable for commissioning to occur
- determine and obtain the resources required to undertake commissioning
- make sure that commissioning is implemented in line with approved procedures and processes
- use information from reliable sources to identify any problems with commissioning activity
- resolve any problems with commissioning activity that are within your area of responsibility
- refer any problems that you cannot resolve to appropriate people at appropriate times
- assess the results of the commissioning to identify the outputs of the network
- confirm that the commissioning procedure complies with approved procedures and practices and with all relevant regulatory requirements
- record results of commissioning activity in appropriate information systems
Knowledge and Understanding
You need to know and understand:
- approved methods and procedures for commissioning
- sources of information including network specifications, statutory and non-statutory reports, company documentation, job instructions, internal and external client documentation
- commissioning activity suitable for different types of network
- factors to take into account when planning commissioning
- conditions that could effect the environment including variations in weather, protected areas, pollution, products, work in adjacent areas, waste management, people's actions
- resource requirements including plant, equipment, materials, labour, consumables
- approved materials and equipment and how to obtain information on availability
- types of problem that could occur and how to resolve them
- water regulations and hygiene procedures related to ensuring the integrity and cleanliness of water supplies and the importance of personal hygiene
- approved procedures, policies, practices, regulations and guidelines relating to health, safety for self and others, environment, emergencies, contingency planning and risk assessments
- how to obtain information on regulations and guidelines
- the impact that commissioning activity could have on other networks
- expected outputs from the network
- how to assess the results of commissioning
- systems for recording information and why it is important to use them
Scope/range
Scope Performance
Scope Knowledge
Values
Behaviours
Skills
Glossary
Links To Other NOS
External Links
Version Number
2
Indicative Review Date
01 Dec 2021
Validity
Legacy
Status
Original
Originating Organisation
Energy & Utility Skills
Original URN
EUSNCO310
Relevant Occupations
Engineering, Water Network Construction Operative, Water Network Construction Supervisor
SOC Code
9225
Keywords
commission, decommission, networks, methods, procedures