Restore water network components to operational condition LEGACY
URN: EUSWNC10L
Business Sectors (Suites): Water Network Construction Operations,Multi-Utility Network Construction Operations
Developed by: Energy & Utility Skills
Approved on:
01 Dec 2018
Overview
This Standard is about restoring water network components to operational condition. This includes the repair and replacement of short sections of mains and fitting temporary or permanent external mechanical fittings on mains or services.
This involves preparing to restore components, carrying out repair or replacement within agreed timescales using approved materials in accordance with company procedures.
This Standard is for water network construction operatives who restore water network components to operational condition.
Performance criteria
You must be able to:
- work in accordance with health and safety, environment and hygiene regulations and legislation
- carry out site specific risk assessment, and review in accordance with company procedures
- select and wear the designated personal protection equipment (PPE)
- repair or replace components in accordance with relevant specifications and work instructions
- prepare components for repair or replacement
- carry out repair or replacement to agreed timescale
- use approved materials and components for repairs or replacements
- make sure that repaired or replaced components meet specified operating conditions and parameters
- carry out all work in accordance with company procedures
- produce accurate and complete records of all work carried out
- deal with problems within your control
- refer problems and conditions outside your responsibility or which you cannot solve to appropriate people
- deal with any emergencies that may arise in line with approved procedures
Knowledge and Understanding
You need to know and understand:
- relevant health, safety and environment legislation, procedures and codes of practice including those governing work in excavations, hazardous materials, accidents and personal protective equipment (PPE)
- the importance of following all hygiene procedures
- how to interpret relevant drawings, plans and specifications
- the various components in use on the water network
- how to repair joints, horizontal and circumferential cracks and breaks, corrosion and interference damage and when replacement is necessary
- how to repair or replace metallic and non-metallic pipes and fittings
- techniques to use to repair components
- component replacement methods for mains and services
- the types of tools and equipment to be used when restoring components to operating condition
- the care and control procedures to be used to ensure compliance with hygiene regulations
- the different types of records and documentation used to record
Scope/range
Scope Performance
Scope Knowledge
Values
Behaviours
Skills
Glossary
Links To Other NOS
External Links
Version Number
2
Indicative Review Date
01 Dec 2021
Validity
Legacy
Status
Original
Originating Organisation
Energy and Utility Skills
Original URN
EUSNCO216
Relevant Occupations
Engineering, Water Network Construction Operative, Water Network Construction Supervisor
SOC Code
8134
Keywords
water, network, operations, utility, utilities