Manage project handover
Overview
"This standard is about confirming that the project requirements meet the stakeholders' expectations, developing, agreeing and following a project handover programme. Identifying, agreeing and arranging for the completion of outstanding work and handing over responsibilities and documentation for the project in accordance with current organisational requirements which are equal to or exceed current statutory and legislative requirements.
This standard is for people working in the occupational area of construction site management which is defined as the management of multiple construction trades and disciplines and can be used by supervisors and managers"
Performance criteria
You must be able to:
"P1 confirm project requirements, consult with stakeholders and
develop, agree and record a handover programme
P2 check that project requirements have been met, or record
outstanding work, including any remedial activities or
defects, in order to agree, arrange and record a satisfactory
completion
P3 carry out handover inspections, relevant tests and
commissioning activities ensuring they are recorded and
certificated
P4 record stakeholder concerns during inspection, agree and
record any actions required
P5 ensure that at least three of the following stakeholders’
respective responsibilities are recorded, accepted and
adopted on handover
5.1 insurance
5.2 security
5.3 operations
5.4 health, safety and wellbeing
5.5 utility supply
5.6 environmental
5.7 sustainability
P6 assemble, record and hand over relevant documentation for
the following in accordance with the project
6.1 manuals and guidance materials
6.2 plans
6.3 operating equipment
6.4 security information and equipment
6.5 certificates
6.6 services
6.7 systems
6.8 equipment
6.9 materials
6.10 maintenance records
6.11 structural design"
Knowledge and Understanding
You need to know and understand:
"Performance Criteria 1
Handover programme
K1 how to consult with stakeholders to confirm the following
project requirements to develop a handover programme
K1.1 time
K1.2 quality
K1.3 cost
K1.4 health and safety
K1.5 sustainability
K1.6 defects rectification period
K1.7 warranties
K2 why it is important a handover programme
Performance Criteria 2
Project requirements and outstanding work
K3 how to check that the following project requirements have
been met
K3.1 time
K3.2 quality
K3.3 cost
K3.4 health and safety
K3.5 sustainability
K3.6 defects rectification period
K3.7 warranties
K4 how to record outstanding work in order to agree and
arrange a satisfactory completion
K5 why it is important to check project requirements and
outstanding work to agree a satisfactory completion
Performance Criteria 3
Handover inspections and tests
K6 how to carry out handover inspections
K7 the range of tests required on handover
K8 how to ensure relevant tests are witnessed by the following
stakeholders
K8.1 client, customer or their representative
K8.2 users
K8.3 consultants
K8.4 contractors
K8.5 regulatory authorities
K9 how to ensure relevant certification is acquired
K10 why it is important handover inspections and certificates
Performance Criteria 4
Stakeholder concerns
K11 how to record the following stakeholders’ concerns during
inspections
K11.1 client, customer or their representative
K11.2 users
K11.3 consultants
K11.4 contractors
K11.5 regulatory authorities
K12 how to agree relevant actions during inspections with
stakeholders
K13 why stakeholders’ concerns need to be addressed
Performance Criteria 5
Stakeholder responsibilities
K14 how to ensure the following accept and adopt the following
responsibilities on handover
Stakeholders
K14.1 client, customer or their representative
K14.2 users
K14.3 consultants
K14.4 contractors
K14.5 regulatory authorities
Responsibilities
K14.6 insurance
K14.7 security
K14.8 operations
K14.9 health, safety and wellbeing
K14.10 utility supply
K14.11 environmental
K14.12 sustainability
K15 why it is required for stakeholders to accept their
responsibilities
Performance Criteria 6
Documentation
K16 how to assemble the following relevant documentation in
accordance with the project
K16.1 manuals and guidance materials
K16.2 plans
K16.3 operating equipment
K16.4 security information and equipment
K16.5 certificates
K16.6 services
K16.7 systems
K16.8 equipment
K16.9 materials
K16.10 maintenance records
K16.11 structural design
K17 how to hand over relevant documentation in accordance with
the project requirements
K18 why it is required to assemble and hand over appropriate
documentation for the project"