Plan and schedule the maintenance activities of property, services or systems

URN: COSVR741
Business Sectors (Suites): Construction Site Management
Developed by: CITB
Approved on: 2020

Overview

"This standard is about producing work programmes and specifications for maintenance activities, sequencing resources for the maintenance activities and ensuring the maintenance activities are completed within the agreed budget, to the agreed quality and within the agreed time in accordance with current organisational requirements which are equal to or exceed current statutory and legislative requirements.
This standard is for people working in the occupational area of construction site management which is defined as the management of multiple construction trades and disciplines and can be used by supervisors and managers"


Performance criteria

You must be able to:

"P1      implement and record regular inspections to confirm the
          project requirements for at least three of the following
          maintenance activities for the following property, services or
          systems:
          Maintenance activities
          1.1     remedial
          1.2     scheduled
          1.3     unscheduled
          1.4     preventative
          1.5     corrective
          1.6     emergency
          Property, services or systems
          1.7     highways
          1.8     traffic controls
          1.9     structures
          1.10   external structure
          1.11   internal structure
          1.12   historical or conservation interests
          1.13   internal fabric
          1.14   external fabric
          1.15   utilities and services
          1.16   landscaping
P2      identify, review and record the consideration of at least four
          of the following influencing factors and three of the following
          guidance materials about the property, service or system to
          be maintained
          Influencing factors
          2.1     organisational requirements
          2.2     project requirements
          2.3     current legislation
          2.4     resource allocation
          2.5     working requirements
          2.6     environmental considerations
          2.7     near neighbours
          2.8     weather conditions
          2.9     ground or site conditions
          2.10   sustainability
          2.11   client, customer or their representative
          2.12   reports and surveys
          2.13   archaeology
          2.14   heritage issues
          2.15   planning or statutory consents
*          Guidance materials*
          2.16   plans, drawings or diagrams
          2.17   owner’s manuals
          2.18   log books
          2.19   maintenance schedules and manuals
          2.20   practice guides and specifications
          2.21   current legislation and official guidance
          2.22   historical data
          2.23   existing records
          2.24   surveys
P3      prioritise and record the maintenance activities to take
          account of identified influencing factors whilst maintaining
          consistency
P4      identify and record at least four of the following changing
          circumstances
          4.1    susceptibility to damage
          4.2    safety requirements
          4.3    need to inhibit, and respond to deterioration
          4.4    weather conditions
          4.5    ground or site conditions
          4.6    environmental conditions
          4.7    use or change of use
          4.8    current legislation
          4.9    resources
          4.10  security threats
          4.11  client, customer or their representative
          4.12  reports and surveys
          4.13  historical data
          4.14  planning or statutory consents
P5      ensure maintenance activity records of actions carried out and
          data collected are current for at least four of the following
          5.1    inspections
          5.2    faults or problems
          5.3    corrective actions
          5.4    costs
          5.5    resources
          5.6    complaints
          5.7    delays
P6      identify, assess and obtain at least two of the following
          necessary resources for maintenance activities
          6.1     people
          6.2     plant, equipment or machinery
          6.3     materials and components
          6.4     sub-contractors
          6.5     information
          6.6     work area and facilities
          6.7     waste management
          6.8     utility providers
P7      prepare plans and schedules for at least three of the following
          maintenance activities and negotiate and agree them with
          stakeholders
          7.1     planned maintenance activities
          7.2     tendered works
          7.3     responsive works
          7.4     preventative maintenance work
          7.5     cost estimated works
          7.6     seasonal maintenance
          7.7     traffic maintenance (signing, lighting and guarding)
          7.8     emergency works
          7.9     contingency plans"


Knowledge and Understanding

You need to know and understand:

"Performance Criteria 1
Project requirements
K1      how to confirm project requirements for the following
          maintenance activities of the following property, systems or
          services
          Maintenance activities
          K1.1    remedial
          K1.2    scheduled
          K1.3    unscheduled
          K1.4    preventative
          K1.5    corrective
          K1.6    emergency

          Property, services or systems
          K1.7     highways
          K1.8     traffic controls
          K1.9     structures
          K1.10   external structure
          K1.11   internal structure
          K1.12   historical or conservation interests
          K1.13   internal fabric
          K1.14   external fabric
          K1.15   utilities and services
          K1.16   landscaping
K2      who to consult with to confirm project requirements
Performance Criteria 2
Identify and review
K3     how to identify and review the following influencing factors
          K3.1     organisational requirements
          K3.2     project requirements
          K3.3     current legislation
          K3.4     resource allocation
          K3.5     working requirements
          K3.6     environmental considerations
          K3.7     near neighbours
          K3.8     weather conditions
          K3.9     ground or site conditions
          K3.10   sustainability
          K3.11   client, customer or their representative
          K3.12   reports and surveys
          K3.13   archaeology
          K3.14   heritage issues
          K3.15   planning and statutory consents
K4      how to identify and review the following guidance materials
          K4.1    plans, drawings or diagrams
          K4.2    owner’s manuals
          K4.3    log books
          K4.4    maintenance schedules and manuals
          K4.5    practice guides and specifications
          K4.6    current legislation and official guidance
          K4.7    historical data
          K4.8    existing records
          K4.9    surveys
K5      why it is important to identify and review influencing factors
          against guidance materials
Performance Criteria 3
Prioritise maintenance activities
K6     how to prioritise and record the maintenance activities to take
         account of identified influencing factors whilst maintaining
         consistency
K7     why it is important to prioritise and record the maintenance
         activities to take account of identified influencing factors
         whilst maintaining consistency
K8      how to assess the following influencing factors
          K8.1     organisational requirements
          K8.2     project requirements
          K8.3     current legislation
          K8.4     resource allocation
          K8.5     working requirements
          K8.6     environmental considerations
          K8.7     near neighbours
          K8.8     weather conditions
          K8.9     ground or site conditions
          K8.10   sustainability
          K8.11   client, customer or their representative
          K8.12   reports and surveys
          K8.13   archaeology
          K8.14   heritage issues
          K8.15   planning and statutory consents
K9      how to prioritise the following maintenance activities
          K9.1     planned maintenance 
          K9.2     tendered works
          K9.3     responsive works
          K9.4     preventative maintenance work
          K9.5     cost estimated work
          K9.6     seasonal maintenance
          K9.7     traffic maintenance (signing, lighting and guarding)
          K9.8     emergency works
          K9.9     contingency plans
K10    why it is important to assess influencing factors and prioritise
          maintenance activities
Performance Criteria 4
Changing circumstances
K11     how to account for the following changing circumstances
            K11.1    susceptibility to damage
            K11.2    safety requirements
            K11.3    need to inhibit, and respond to deterioration
            K11.4    weather conditions
            K11.5    ground or site conditions
            K11.6    environmental conditions
            K11.7    use or change of use
            K11.8    current legislation
            K11.9    resources
            K11.10  security threats
            K11.11  client, customer or their representative
            K11.12  reports and surveys
            K11.13  historical data
            K11.14  planning and statutory consents
K12      how to amend priorities when reviewing the following
            influencing factors:
            K12.1     organisational requirements
            K12.2     project requirements
            K12.3     current legislation
            K12.4     resource allocation
            K12.5     working requirements
            K12.6     environmental considerations
            K12.7     near neighbours
            K12.8     weather conditions
            K12.9     ground or site conditions
            K12.10   sustainability
            K12.11   client, customer or their representative
            K12.12   reports and surveys
            K12.13   archaeology
            K12.14   heritage issues
            K12.15   planning and statutory consents
Performance Criteria 5
Recording systems
K13    why activity records and data collected for the following
          work and maintenance activities needs to be current
          Activity records and data collected
          K13.1     inspections
          K13.2     faults or problems
          K13.3     corrective actions
          K13.4     costs
          K13.5     resources
          K13.6     complaints
          K13.7     delays
          Maintenance work
          K13.8    remedial
          K13.9    scheduled
          K13.10  unscheduled
          K13.11  preventative
          K13.12  corrective
          K13.13  emergency
          Maintenance activities
          K13.14   planned maintenance work
          K13.15   tendered works
          K13.16   responsive works
          K13.17   preventative maintenance work
          K13.18   cost estimated work
          K13.19   seasonal maintenance
          K13.20   traffic maintenance (signing, lighting and guarding)
          K13.21   emergency works
          K13.22   contingency plans
K14    how to ensure that records of the following activities and data
          are current
          K14.1     inspections
          K14.2     faults or problems
          K14.3     corrective actions
          K14.4     costs
          K14.5     resources
          K14.6     complaints
          K14.7     delays
Performance Criteria 6
Resources
K15    how to identify the following necessary resources for
          maintenance activities
          Resources
          K15.1    people
          K15.2    plant, equipment or machinery
          K15.3    materials and components
          K15.4    sub-contractors
          K15.5    information
          K15.6    work area and facilities
          K15.7    waste management
          K15.8    utility providers
          Maintenance activities
          K15.9    planned maintenance work
          K15.10  tendered works
          K15.11  responsive works
          K15.12  preventative maintenance work
          K15.13  cost estimated work
          K15.14  seasonal maintenance
          K15.15  traffic maintenance (signing, lighting and guarding)
          K15.16  emergency works
          K15.17  contingency plans
K16    how to assess the quantity and quality of resources for
          maintenance activities
K17    how to maintain the necessary resources for the maintenance
          work of the following property, systems or services
          K17.1    highways
          K17.2    traffic controls
          K17.3    structures
          K17.4    external structure
          K17.5    internal structure
          K17.6    historical or preservation interests
          K17.7    internal fabric
          K17.8    external fabric
          K17.9    utilities and services
          K17.10  landscaping
Performance Criteria 7
Plans and schedules
K18    how to prepare plans and schedules for the following
          maintenance activities
          K18.1    planned maintenance work
          K18.2    tendered works
          K18.3    responsive works
          K18.4    preventative maintenance work
          K18.5    cost estimated work
          K18.6    seasonal maintenance
          K18.7    traffic maintenance (signing, lighting and guarding)
          K18.8    emergency works
          K18.9    contingency plans
K19    how to negotiate and agree plans and schedules with
          decision-makers
K20    why it is important plans and schedules for the following
          maintenance activities
          K20.1   planned maintenance work
          K20.2   tendered works
          K20.3   responsive works
          K20.4   preventative maintenance work
          K20.5   cost estimated work
          K20.6   seasonal maintenance
          K20.7   traffic maintenance (signing, lighting and guarding)
          K20.8   emergency works
          K20.9   contingency plans"


Scope/range


Scope Performance


Scope Knowledge


Values


Behaviours


Skills


Glossary


Links To Other NOS


External Links


Version Number


Indicative Review Date

2025

Validity

Current

Status

Original

Originating Organisation

CITB

Original URN

VR741

Relevant Occupations

Production Managers and Directors in Construction

SOC Code

1122

Keywords

Maintenance; Remedial; Property; Services; Unscheduled; Preventative; Emergency