Erect and dismantle independent and birdcage scaffolds

URN: COSVR247
Business Sectors (Suites): Accessing Operations and Rigging (Construction)
Developed by: CITB
Approved on: 2020

Overview

"​This standard is about preparing, erecting and dismantling independent and birdcage scaffolds, interpreting information, adopting safe, healthy and environmentally responsible work practices, selecting and using materials, components, tools and equipment.
This standard is for people working in the occupational area of Scaffolding and can be used by operatives, supervisors and managers."


Performance criteria

You must be able to:

"​P1     interpret the given information relating to the work and
         resources to confirm its relevance
P2     comply with the given, relevant legislation and official
         guidance to carry out your work and maintain safe and healthy
         work practices
P3     select the required quantity and quality of resources for the
         methods of work
P4     comply with organisational procedures to minimise the risk of
         damage to the work and surrounding area
P5     comply with the given contract information to carry out the
         work efficiently to the required specification
P6     complete the work within the allocated time, in accordance
         with the programme of work"


Knowledge and Understanding

You need to know and understand:

"Performance Criteria 1
Interpretation of information
K1     organisational procedures developed to report and rectify
         inappropriate information and unsuitable resources, and how
         they are implemented
K2     types of information, their source and how they are
         interpreted
K3     the organisational procedures to solve problems with the
         information and why it is important they are followed
Performance Criteria 2
Safe work practices
K4     current legislation and official guidance and how it is
         applied
K5     how emergencies should be responded to and who should
         respond
K6     the organisational security procedures for tools, equipment
         and personal belongings
K7     the accident reporting procedures are and who is responsible
         for making the report
K8     why, when and how health and safety control equipment
         should be used
K9     how to comply with environmentally responsible work
         practices to meet current legislation and official guidance
Performance Criteria 3
Selection of resources
K10   the characteristics, quality, uses, limitations and defects
         associated with the resources and how defects should be
         rectified
K11   how the resources should be used and how any problems
         associated with the resources are reported
K12   the organisational procedures to select resources, why they
         have been developed and how they are used
K13   the hazards associated with the resources and methods of
         work and how they are overcome
Performance Criteria 4
Minimise the risk of damage
K14   how to protect work from damage and the purpose of
         protection
K15   why disposal of waste should be carried out safely and how it
         is achieved
Performance Criteria 5
Meet the contract specification
K16   how methods of work, to meet the specification, are carried
         out and problems reported
K17   how maintenance of tools and equipment is carried out
Performance Criteria 6
Allocated time
K18   what the programme is for the work to be carried out in the
         estimated, allocated time and why deadlines should be kept"


Scope/range


Scope Performance

"Performance Criteria 1
1      interpret plans, drawings, sketches, method statements,
        risk assessments, specifications, schedules and manufacturers'
        information related to the work to be carried out
Performance Criteria 2
2      avoid risk by following the given information relating to
        the following:
        2.1     methods of work
        2.2     safe use of health and safety control equipment
        2.3     safe use of access equipment
        2.4     safe use, storage and handling of materials, tools and
                  equipment
        2.5     specific risks to health
Performance Criteria 3
3      select resources associated with own work:
        3.1     materials, components, fixings, anchors and ties
        3.2     tools and equipment
        3.3     access equipment
Performance Criteria 4
4      protect the work and its surrounding area from damage
5      maintain a clear and tidy workspace
6      dispose waste in accordance with current legislation
Performance Criteria 5
7      demonstrate work skills to measure, set out, assemble, fix,
        position, secure and remove
8      use and maintain hand tools, portable power tools and access
        equipment
9      erect and dismantle independent and birdcage scaffolds to
        given working instructions for one of the following:
        9.1     tube and fitting
        9.2     systems scaffold
10      erect and dismantle bridging beam work within either
          independent or birdcage scaffold
Performance Criteria 6
11      complete own work within the estimated, allocated time
          to meet the needs of other occupations and/or client"
Z


Scope Knowledge

"Disposal of waste
1      environmental responsibilities, organisational procedures,
        manufacturers' information, statutory regulations and official
        guidance
Emergencies
2      operative's response to situations in accordance with
        organisational authorisation and personal skills when involved
        with:
        2.1    fires, spillages, injuries
        2.2    emergencies relating to occupational activities
Hazards
3      those identified by risk assessment, method of work,
        manufacturers' technical information, statutory regulations and
        official guidance
Health and safety control equipment
4      identified by the principles of prevention for occupational use,
        types and purpose of each type, work situations and general
        work environment:
        4.1    collective protective measures
        4.2    local exhaust ventilation (LEV)
        4.3    personal protective equipment (PPE)
        4.4    respiratory protective equipment (RPE)
Information
5      plans, drawings and sketches, specifications, schedules, method
        statements, risk assessments, manufacturers' technical
        information, regulations and official guidance associated with
        scaffolding work
Legislation and official guidance
6      responsibilities regarding potential accidents, health
        hazards and the environment whilst working in the workplace,
        below ground level, in confined spaces, at height, with tools
        and equipment, with materials and substances, with movement
        storage of materials by manual handling and
        mechanical lifting
Maintenance
7      operative care of hand tools, portable power tools, ancillary
        equipment and access equipment
Methods of work
8      application of knowledge for safe work practices, procedures
        and skills, relating to the method and area of work and
        materials used to:
        8.1    confirm the area to erect the independent and birdcage
                 scaffolds
        8.2    confirm that the stability of the foundation and structure
                 on which the scaffold will be erected and secured has
                 been considered
        8.3    identify the technical differences between independent
                 and birdcage scaffolds
        8.4    confirm the materials and component make-up (tube and
                 fitting, systems scaffolds)
        8.5    set out and prepare for the erection of independent and
                 birdcage scaffolds
        8.6    erect and secure scaffolds
        8.7    dismantle and remove independent and birdcage
                 scaffolds
        8.8    visually inspect fall protection equipment
        8.9    install ties and test anchors 
        8.10  work with, around and in close proximity to plant and
                 machinery
        8.11  use hand tools, and ancillary equipment
        8.12  work at height
        8.13  use access equipment
9      teamwork and communication
10    needs of other occupations associated with erecting and
        dismantling independent and birdcage scaffolds
Problems
11     those arising from information, resources and methods of
         work:
         11.1    own authority to rectify
         11.2    organisational reporting procedures
Programme
12      types of progress charts, timetables and estimated times
13      organisational procedures for reporting circumstances which
          will affect the work programme
Protect work
14      protect work against damage from general workplace
          activities, other occupations and adverse weather conditions
Resources
15      materials, components and equipment relating to types,
          quantity, quality, sizes and sustainability of standard and
          specialist:
          15.1    tube and fitting
          15.2    systems scaffold
          15.3    associated materials (props, ropes, anchors, ties,
                     boards, plates, beams, ladders, proprietary
                     components)
          15.4    hand tools, portable power tools and ancillary
                     equipment
16      confirm resources and materials conform with the
          specification
17      methods of calculating quantity, length and area associated
          with the method and procedure to erect and dismantle
          independent and birdcage scaffolds
Security procedures
18      site, workplace, company and operative, vehicles"


Values


Behaviours


Skills


Glossary


Links To Other NOS


External Links


Version Number

3

Indicative Review Date

2025

Validity

Current

Status

Original

Originating Organisation

CITB

Original URN

COSVR247

Relevant Occupations

Scaffolders, Stagers and Riggers

SOC Code

8151

Keywords

Independent; Birdcage; Scaffolds; Tube and fitting; Props; Ladders; Systems-scaffold