Shutting down equipment in downstream operations
Overview
This standard addresses your competence in shutting down equipment.
This standard deals with the following:
  
  
1 Prepare to shut down  
2 Shut down equipment  
During this work you must take account of the relevant operational requirements and safe working practices AS THEY APPLY TO YOU.  
This Standard is suitable for those working in the downstream fuel environment.  
  
Previous version:
  
Adapted from Unit 7 of Refinery Field Operations NOS – version April 2005
Performance criteria
You must be able to:
P1 obtain appropriate confirmation for shutdown to proceed  
P2 correctly identify equipment and check status  
P3 correctly follow procedures for checks and tests  
P4 inform all relevant people of possible impact on them due to shutdown  
P5 inform appropriate personnel that shutdown is imminent  
P6 correctly shut down equipment in accordance with specified procedures  
P7 identify, correct and promptly report abnormalities  
P8 complete all relevant documentation  
P9 inform appropriate personnel when shutdown is completed to specified state  
P10 work safely in accordance with operational requirements
Knowledge and Understanding
You need to know and understand:
K1 how to select, use and care for PPE   
K2 the implications of statutory and organisational requirements  
K3 how to interpret operational requirements   
K4 the importance of shutting down the equipment in the correct sequence  
K5 the consequence of shutting down the equipment too quickly or too slowly or in the wrong sequence  
K6 the operating principles of relevant equipment   
K7 trip systems and logic sequences  
K8 plant layout and plant operating manuals  
K9 equipment shutdown procedures  
K10 how to work with and within the Permit to Work system  
K11 how to access relevant documentation   
K12 the function of the equipment to be started in the operation of the plant and process  
K13 the properties of the material contained in the equipment  
K14 the potential problems and appropriate action to be taken in preparing for shutdown  
K15 the effect on the remainder of the plant where the item of equipment is taken out of service  
K16 the effect on plant in adjacent areas  
K17 the situations when shutdown should not proceed  
K18 the potential problems and appropriate action to be taken if item of equipment is not shut down correctly  
K19 the consequences if item of equipment is not isolated correctly  
K20 the importance of time taken to shut down and isolate item of equipment to specified state  
K21 the operating conditions and parameters